NASA’s SLS Moon rocket is 2 years behind and billions over budget, internal report finds

5 min • 12 mars 2020
NASA’s ambitious plan to put boots on the Moon in 2024 is looking increasingly costly — and increasingly unlikely — if the current cost overruns and delays are any indication, according to a report by the agency’s Office of the Inspector General. “NASA’s continued struggle with managing SLS Program costs and schedule has the potential to impact the Agency’s ambitious goals for the Artemis program,” reads the report issued yesterday.

Learn more about your ad choices. Visit podcastchoices.com/adchoices